refer03.jpg

Project name: 132 KVA overhead lines in Ramadi.

Client: Gulf Region Division-Central District

W6EX GRD Central District

APO AE 09335

POC: Jose Morales@tac01.usace.army.mil

Description: Construction of 132 KVA overhead line from Ar Ramadi east to Heet. 4 types of high tension towers were used.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad and Amman offices are supporting the administration and correspondences. The site staff was completely from the local area to encourage employment in war affected area. Total 9 engineers, 25 technicians and 10 administration high educated staff are covering the project activities.

Start Date: October 2006

Completion date: October 2007


refer04.jpg

refer05.jpg

Project name: 33/11 new Hsibah substation.

Client: Secure Global Engineering

POC: Ayham Al Yassiry, tel: +964 790 1745 534, E-mail: ayham@sge-iraq.com

Description: Construction of 33/11 new Hsibah substation. The works include construction of buildings delivery and install equipment, commissioning, training and all necessary connections. Most equipment is delivered from Siemens.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Amman branc office is supporting the administration and correspondence. The site staff was completely from the local area to encourage employment in war affected area. Total 18 engineers, 45 technicians and 12 administration high educated staff are covering the project activities.

Start Date: October 2006

Completion date: October 2007


refer06.jpg

refer07.jpg

Project name: Design & Construct of Asphalt road in Buhriz-Baquba.

Client: CAPE Environmental

POC: James Stewart tel: +1732 610 9692, E-mail: jstewart@cape-inc.com

Description: Construction of new 4-lanes road connecting the main Baghdad-Baquba road and Bhiriz city crossing Dyala River over Buhriz Bridge. The university of Baghdad were doing the QC, The National State laboratory was responsible for all  field and laboratory tests.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 8 engineers, 18 technicians and 8 administration high educated staff are covering the project activities.

Start Date: January 2005

Completion date: August 2005


refer08.jpg

refer09.jpg

Project name: Design & Construct Facilities for ING Batt. in Suwaira.

Client: CAPE Environmental

POC: James Stewart tel: +1732 610 9692, E-mail: jstewart@cape-inc.com

Description: Design, Renovation and New Construction of 17000m2. The project includes infrastructure, roads and training yards, and power supply facilities. The project completed within record time of less than 90 days.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 30 engineers, 64 technicians and 15 administration high educated staff are covering the project activities. More than 1300 of skilled and unskilled were engaged from the local area.

Start Date: Jun 2005

Completion date: September 2005


refer10.jpg

refer11.jpg

refer12.jpg

Project name: Buhriz Bridge on Dyala River in Dyala.

Client: CAPE Environmental

POC: James Stewart tel: +1732 610 9692, E-mail: jstewart@cape-inc.com

Description: Surveying, engineering and Construction of 220m concrete bridge on Dyala River in Buhriz, 50km east of Baghdad. The bridge contains 7 concrete gorders span 24m each, and middle span 48m width steel girder. The bridge is connecting the main Baghdad Baquba road and Bhiriz city. The university of Baghdad were doing the QC, The National State laboratory was responsible for all  field and laboratory tests.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 16 engineers, 35 technicians and 8 administration high educated staff are covering the project activities.

Start Date: November 2005

Completion date: December 2006


refer13.jpg

refer14.jpg

refer15.jpg

Project name: Omar Bn Abdulaziz Bridge on Warrar River in Ramadi.

Client: CAPE Environmental

POC: James Stewart tel: +1732 610 9692, E-mail: jstewart@cape-inc.com

Description: Surveying, engineering and Construction of 220m concrete bridge on Warrar River in the center of Ramadi, 80km West of Baghdad. The bridge contains 9 concrete prestressd girders 24m each. The University of Baghdad and the University of Ramadi were doing the QC, The National State laboratory was responsible for all field and laboratory tests.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 18 engineers, 45 technicians and 10 administration high educated staff are covering the project activities.

Start Date: November 2005

Completion date: December 2006


refer16.jpg

refer17.jpg

Project name: QTM & QRF Facilities in Baghdad .

Client: CAPE Environmental

POC: James Stewart tel: +1732 610 9692, E-mail: jstewart@cape-inc.com

Description: Design and Construct Inf. Brg. at QTM @ QEF. The site is located in Abu Graib, the most hot and dangerous area. The project contains about 50000m2 of new construction and rehabilitation. Including schools, mosque, clinic, training facilities, power generation plants, infrastructure, water and sewage facilities. The most challenge was the short time and very dangerous area. The University of Baghdad is the QC with more than 40 engineers monitoring and estimating the quality of works. The National State laboratory was responsible for all field and laboratory tests.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. About 2000 workers were in the site with more than 30 engineers, 200 technicians and more than 20 experts for administration.

Start Date: October 2005

Completion date: April 2006

refer18.jpg

refer19.jpg

about1.jpg

Project name: NATO Enclave.

Client: NAMSA

POC: TOXIE H. COURTNEY, DSN: 606-640-2681, Comm: 081-721-2681 E-mail: tcourtney@afsouth.nato.int, toxcourt@yahoo.com

Description: The project contains several subcontracts, includes, clinic, accommodation building, Force protection projects, infrastructure monitoring system with night vision, with power generating plants. The The National State laboratory was responsible for all field and laboratory tests.

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. Total 12 engineers, 45 technicians and 10 administration high educated staff are covering the project activities.

Start Date: November 2005

Completion date: works in progress

refer20.jpg

refer21.jpg


 Project name: Dubuni water treatment palnt

Client: Waset water directorate

POC: Eng. Mohammad Mortada

 

Description: The work include clearing the site and construction concrete steel reinforced foundation of the equipments with guard house and brick fence 

- supplying complete water treatment plant including clarifier and settling tank , filtration vessel , feed water pumps, chlorination dosing system , aluminum sulfate predation tank with dosing pump, backup generators, transformers, intake steel structure and UPVC   6 inch and 4 inch water distribution network  more than 7500 meter

 

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad office and Amman are supporting the administration and correspondence. The site staff was completely The site staff was completely from the local area to encourage employment in war affected area. Beside hundreds of skilled and unskilled workers, Total 12 engineers, 20 technicians and 10 administration high educated staff are covering the project activities.

 

Start Date: May 2007

Completion date: September 2007

 


 

Project name: Mehrot irrigation project, lining irrigation canals.

 

Client: Diyala water directorate

 

POC: Diyala water directorate

 

Description: Mehrut irrigstion project is located in Diyala governorate, AL- Miqdadiyah, AL wajehea province. Lining contains 2 layers of concrete, with total quantity of about 50,000m3.  modern equipment and concrete additives suitable for this area were used.

 

Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad office and Amman are supporting the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Beside hundreds of skilled and unskilled workers, Total 12 engineers, 20 technicians and 10 administration high educated staff are covering the project activities.

 

Start Date: May 2005

Completion date: January 2006

 

 

 

refer22.jpg

refer23.jpg

Many projects were done as well before 2000

  • Construction and finishing works of 3 hospitals MCP project in Baghdad, Swaira and Kut. Federal Directorate for Supplying and Procurement. 1989-1991.
  • Participation in design and construction of 216 school project from prefabricated concrete elements in Baghdad,
  • Supplying of medical equipment to the ministry of health.
  • Residential and administration building in Baghdad and the middle zone of Iraq.
  • High ways, asphalt roads in the middle zone of Iraq.
  • Water treatment plants in the middle zone of Iraq.
  • Highline towers in the middle zone of Iraq on behalf of Energo Invest Co.
  • Highline towers in the west part of Iraq on behalf of Electrical distribution Company.
  • Several industrial buildings in the Textile State Company in Baghdad from 1987-1990.
  • Finishing works and road furniture in the expressway no.1 R-4, from 1989-1992. The job included wire fence, guardrail, asphalt curb, traffic signs, horizontal signalizations, irrigation canals, embankment slopes. The employer was Union Engineering Company from Yugoslavia.
  • Finishing works in the expressway no.1 R-4-Section A, during 1989-1990. The job included wire fence, guardrail, asphalt curb, traffic signs, horizontal signalizations, irrigation canals, embankment slopes. The employer was AUTOPUT Company from Yugoslavia.
  • Execution of finishing works in the expressway no.1 R-4-Section B, during 1989-1990. The job included wire fence, guardrail, asphalt curb, traffic signs, horizontal signalization, irrigation canals, embankment slopes. The employer was PLANUM Company from Yugoslavia.
  • Finishing works in the expressway no.1 R-4, in 1990. The employer was, Directorate of Expressways, State Company for Roads and Bridges, the Ministry of Housing.
  • Horizontal signalizations of Faluja - Amiria Road, the bridge over Alfurat, 1990, Al Fao states Co.
  • Steel overhead bridges for vehicle height fixing in Yousufia freeway, 1990.
  • Several works for Taj al Maarik State Company in Mousul.
  • Asphalt works in Khanaqeen in Diyala province 1990-1991.
  • Asphalt works in Al saadiya in Diyala province 1990-1991.
  • Disassembling, mounting, erection and commissioning of concrete batching plant in Al Rustamiya Water Treatment Plant, Al Farouk State Company 1990.
  • Disassembling, mounting, erection and commissioning of asphalt batching plant in Dyala, Governorate of Dyala 1990.
  • Delivery of several construction materials for the Governorate of Diyala.
  • Execution of finishing works and measurements in the projects 1100, Baladruz, Al Kasak, and Numania, for FDSP Co. 1989-2003
  • Several works for Union Engineering co. from Yugoslavia, Yugoimport Co. from Yugoslavia, Transcopmlect co. from Bulgaria, Technoprom export from Russia. The works include, concrete works, asphalt works, delivery of hundreds thousands cubic meters of construction materials.
  • Road marking for several roads in the middle zone of Iraq.
  • Several subcontracts for private, state, domestic, and foreign companies.
  • Several surveying, design and measurement works on behalf of private sector in Iraq.
  • Many construction projects in progress.
  • Company equipments to facilitate our projects

    • 6 Concrete Plants with a total capacity of 180m3/h.
    • 4 Gravel Crushing Plants with total production capacity of 1000m3/day for production of several sizes of crushed gravel.
    • 2 Plants for Production of Precast Concrete Elements.
    • Factory for Steel Structures and Steel Elements; up to 10t element.
    • Several types of equipment for building, roads and earth works.
    • Very high transport capacity of all kinds of construction materials.
  •  
       