Danube for Engineering & General Contracting
References
These are a sample of our works after 2000
Note: This page is under reconstruction and updating
Project name: 132 KVA overhead lines in Ramadi.
Client: Gulf Region Division-Central District
W6EX GRD Central District
APO AE 09335
POC: Jose Morales@tac01.usace.army.mil
Description: Construction of 132 KVA overhead line from Ar Ramadi east to Heet. 4 types of high tension towers were used.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad and Amman offices are supporting the administration and correspondences. The site staff was completely from the local area to encourage employment in war affected area. Total 9 engineers, 25 technicians and 10 administration high educated staff are covering the project activities.
Start Date: October 2006
Completion date: October 2007
Project name: 33/11 new Hsibah substation.
Client: Secure Global Engineering
POC: Ayham Al Yassiry, tel: +964 790 1745 534, E-mail: ayham@sge-iraq.com
Description: Construction of 33/11 new Hsibah substation. The works include construction of buildings delivery and install equipment, commissioning, training and all necessary connections. Most equipment is delivered from Siemens.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Amman branc office is supporting the administration and correspondence. The site staff was completely from the local area to encourage employment in war affected area. Total 18 engineers, 45 technicians and 12 administration high educated staff are covering the project activities.
Project name: Design & Construct of Asphalt road in Buhriz-Baquba.
Client: CAPE Environmental
POC: James Stewart tel: +1732 610 9692, E-mail: jstewart@cape-inc.com
Description: Construction of new 4-lanes road connecting the main Baghdad-Baquba road and Bhiriz city crossing Dyala River over Buhriz Bridge. The university of Baghdad were doing the QC, The National State laboratory was responsible for all field and laboratory tests.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 8 engineers, 18 technicians and 8 administration high educated staff are covering the project activities.
Start Date: January 2005
Completion date: August 2005
Project name: Design & Construct Facilities for ING Batt. in Suwaira.
Description: Design, Renovation and New Construction of 17000m2. The project includes infrastructure, roads and training yards, and power supply facilities. The project completed within record time of less than 90 days.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 30 engineers, 64 technicians and 15 administration high educated staff are covering the project activities. More than 1300 of skilled and unskilled were engaged from the local area.
Start Date: Jun 2005
Completion date: September 2005
Project name: Buhriz Bridge on Dyala River in Dyala.
Description: Surveying, engineering and Construction of 220m concrete bridge on Dyala River in Buhriz, 50km east of Baghdad. The bridge contains 7 concrete gorders span 24m each, and middle span 48m width steel girder. The bridge is connecting the main Baghdad Baquba road and Bhiriz city. The university of Baghdad were doing the QC, The National State laboratory was responsible for all field and laboratory tests.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 16 engineers, 35 technicians and 8 administration high educated staff are covering the project activities.
Start Date: November 2005
Completion date: December 2006
Project name: Omar Bn Abdulaziz Bridge on Warrar River in Ramadi.
Description: Surveying, engineering and Construction of 220m concrete bridge on Warrar River in the center of Ramadi, 80km West of Baghdad. The bridge contains 9 concrete prestressd girders 24m each. The University of Baghdad and the University of Ramadi were doing the QC, The National State laboratory was responsible for all field and laboratory tests.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Total 18 engineers, 45 technicians and 10 administration high educated staff are covering the project activities.
Project name: QTM & QRF Facilities in Baghdad .
Description: Design and Construct Inf. Brg. at QTM @ QEF. The site is located in Abu Graib, the most hot and dangerous area. The project contains about 50000m2 of new construction and rehabilitation. Including schools, mosque, clinic, training facilities, power generation plants, infrastructure, water and sewage facilities. The most challenge was the short time and very dangerous area. The University of Baghdad is the QC with more than 40 engineers monitoring and estimating the quality of works. The National State laboratory was responsible for all field and laboratory tests.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. About 2000 workers were in the site with more than 30 engineers, 200 technicians and more than 20 experts for administration.
Start Date: October 2005
Project name: NATO Enclave.
Client: NAMSA
POC: TOXIE H. COURTNEY, DSN: 606-640-2681, Comm: 081-721-2681 E-mail: tcourtney@afsouth.nato.int, toxcourt@yahoo.com
Description: The project contains several subcontracts, includes, clinic, accommodation building, Force protection projects, infrastructure monitoring system with night vision, with power generating plants. The The National State laboratory was responsible for all field and laboratory tests.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad HQ supported the administration and correspondence. Total 12 engineers, 45 technicians and 10 administration high educated staff are covering the project activities.
Project name: Dubuni water treatment palnt
Client: Waset water directorate
POC: Eng. Mohammad Mortada
Description: The work include clearing the site and construction concrete steel reinforced foundation of the equipments with guard house and brick fence
- supplying complete water treatment plant including clarifier and settling tank , filtration vessel , feed water pumps, chlorination dosing system , aluminum sulfate predation tank with dosing pump, backup generators, transformers, intake steel structure and UPVC 6 inch and 4 inch water distribution network more than 7500 meter
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad office and Amman are supporting the administration and correspondence. The site staff was completely The site staff was completely from the local area to encourage employment in war affected area. Beside hundreds of skilled and unskilled workers, Total 12 engineers, 20 technicians and 10 administration high educated staff are covering the project activities.
Start Date: May 2007
Completion date: September 2007
Project name: Mehrot irrigation project, lining irrigation canals.
Client: Diyala water directorate
POC: Diyala water directorate
Description: Mehrut irrigstion project is located in Diyala governorate, AL- Miqdadiyah, AL wajehea province. Lining contains 2 layers of concrete, with total quantity of about 50,000m3. modern equipment and concrete additives suitable for this area were used.
Staff details: Site office with high experienced engineers and technicians managing the site activities, Outside Iraq offices are supporting the project by purchasing equipment and instruments, Baghdad office and Amman are supporting the administration and correspondence. The site staff was mainly from the local area to encourage employment in war affected area. Beside hundreds of skilled and unskilled workers, Total 12 engineers, 20 technicians and 10 administration high educated staff are covering the project activities.
Start Date: May 2005
Completion date: January 2006
Many projects were done as well before 2000
Company equipments to facilitate our projects